Smile Politely

Assembly Hall releases renovation details

Here’s some information coming from the Fighting Illini Loyalty board that unveils serious detail about the upcoming renovations to Assembly Hall.

  • Construction: March 2014 — November 2016
  • Project cost: $160M.
  • Student floor seating will increase from 700 to 1,200.
  • Team benches will be relocated to east side, behind new Orange Krush section.
  • Capacity (16,618) will go down, final capacity will be 15,200-15,300. Most lost seats in A Section & B Section.
  • All seats will be orange or blue.
  • West side will remain the main entrance.
  • 75% of project is funded by philanthropy, individual & corporate.
  • A new circle drive entrance will be built on the east side.
  • New scoreboard and ribbon boards.
  • Escalators.
  • Each suite designed for 14 comfortably, can fit up to 18.
  • All concourses widened, more restrooms on each level.
  • Minor renovation to the roof, nothing drastic.
  • Every inch of the building will be renovated.
  • Project will be done in stages.
  • Illini basketball team will *not* be displaced during construction.
  • AECOM design was in place fall of 2012. Now, in fund raising mode.
  • Luxury seating accounts for 10% of total seats.
  • RT @MarcusJ_NG #illini AD Thomas: Not where they want to be with fundraising, but making progress and confident it will continue to move along.
  • RT @MarcusJ_NG #illini AD Thomas: Making progress toward securing funds for naming rights. Still chipping away at all of it.
  • RT @MarcusJ_NG #illini AD Thomas: There is possibly an interest in hosting NCAA games for men and women.

Executive Editor

More Articles